| No. | Description | Start | Finish | Work (days) |
|---|---|---|---|---|
| 1 | Identify Customer Needs | Apr 3 | Apr 28 | 20 |
| 2 | Delegate Tasks | May 1 | May 5 | 5 |
| 3 | Research Analysis | May 8 | Jun 30 | 40 |
| 4 | Develop Mathematical Model | Jul 3 | Jul 14 | 10 |
| 5 | Benchmarking | Jul 3 | Jul 14 | 10 |
| 6 | Setup Wiki Page | Jul 3 | Jul 14 | 10 |
| 7 | Material Selection Research | Jul 3 | Jul 14 | 10 |
| 8 | Preliminary Design | Jul 17 | Jul 28 | 10 |
| 9 | Develop Budget Plan | Jul 17 | Jul 28 | 10 |
| 10 | Develop Manufacturing Plan | Jul 17 | Jul 28 | 10 |
| 11 | Fan Research | Jul 17 | Jul 28 | 10 |
| 12 | Humidifier Research | Jul 17 | Jul 28 | 10 |
| 13 | Shell/Interior Research | Jul 17 | Jul 28 | 10 |
| 14 | Purchase Materials | Jul 17 | Aug 11 | 20 |
| 15 | Build Prototype | Aug 14 | Sep 28 | 20 |
| 16 | Experimental Prototyping | Sep 11 | Oct 6 | 20 |
| 17 | Product Review | Oct 9 | Oct 20 | 10 |
| 18 | Customer Feedback | Oct 9 | Oct 20 | 10 |
| 19 | Design Modifications | Oct 23 | Nov 3 | 10 |
| 20 | Tornado Control Process | Nov 6 | Nov 17 | 10 |
| 21 | Implement Measurement System | Nov 6 | Nov 17 | 10 |
| 22 | Experimental Data Acquisition | Nov 20 | Dec 1 | 10 |
| 23 | Electronics Configuration | Nov 20 | Dec 1 | 10 |
| 24 | Tornado Characterization | Nov 20 | Dec 1 | 10 |
| 25 | Product Review | Dec 4 | Dec 15 | 10 |
| 26 | Customer Review | Dec 4 | Dec 15 | 10 |
| 27 | Research Design Modifications | Dec 18 | Dec 22 | 5 |
| 28 | Build Final Prototype | Dec 25 | Feb 16 | 40 |
| 29 | Prototype Testing | Feb 19 | Mar 2 | 10 |
| 30 | Additional Improvements | Mar 5 | Apr 13 | 20 |
| 31 | Final Product Review | Apr 2 | Apr 6 | 5 |
| 32 | Final Customer Review | Apr 2 | Apr 6 | 5 |
| 33 | Design Day Poster | Apr 9 | Apr 24 | 12 |
Page last modified on August 29, 2006, at 11:16 AM